CuNi Piping & ANSI Flange Package for Offshore Platform Seawater System

Published | 2 min read
Qiangbin Zhu, Founder of Hicool

Qiangbin Zhu

Founder, Hicool Machinery

Expertise: 10+ years in marine & industrial equipment sourcing. Supplies equipment with CCS, BV or ABS class certificates for vessels and industrial facilities.

CuNi Piping & ANSI Flange Package for Offshore Platform Seawater System
Table of Contents

    Project Overview

    An offshore production platform undergoing seawater cooling system expansion required CuNi 90/10 piping and matching ANSI flanges. The project involved extending the existing seawater intake and distribution system to support new processing modules.

    Challenge

    • CuNi 90/10 pipe — long lead time material, typically 10-14 weeks from mills
    • ABS certification required for all piping components
    • ASTM B467 (pipe) and B171 (flanges) material specifications
    • Mixed sizes: 2" to 10" NPS across the system
    • Flanges: ANSI B16.5, Class 150, RF face — 47 flanges in 6 sizes

    Our Solution

    Hicool sourced from a specialized CuNi manufacturer with ABS production approval and mill stock:

    • CuNi 90/10 Seamless Pipe — 380 meters total, sizes 2" to 10" NPS, Schedule 10S
    • 47× ANSI B16.5 Flanges — CuNi 90/10, Class 150, RF, sizes matching pipe schedule
    • Fittings Package — elbows, tees, reducers in CuNi 90/10, butt-weld ends
    • All items with ABS mill certificates and 3.1 inspection certificates

    Results

    • 35-day delivery — leveraging manufacturer's CuNi billet stock to bypass mill lead time
    • ABS survey at mill passed with zero findings
    • Dimensional inspection: 100% of flanges within ANSI tolerance
    • Material cost approximately 30% below European CuNi suppliers

    Key Takeaway

    CuNi piping projects are typically constrained by material lead times. Sourcing from Chinese manufacturers with existing CuNi billet inventory and ABS production approval can cut delivery from 14 weeks to 5 weeks — critical for offshore platform schedules with limited weather windows.

    Qiangbin Zhu, Founder of Hicool

    Written by

    Qiangbin Zhu

    Founder — Taizhou Hicool Machinery Co., Ltd.

    Qiangbin has been sourcing marine and industrial equipment from China's top manufacturers since 2015. He specializes in supplying equipment with CCS, BV or ABS class certificates. He holds deep relationships with factories across Jiangsu, Zhejiang, and Shandong provinces.

    Need Help Sourcing This Equipment?

    Get quotations with classification society certification, factory test reports, and competitive FOB pricing from verified Chinese manufacturers.

    10+ Years Industry Experience
    CCS · BV · ABS Certified Products
    7–45 Days Delivery Window